Punjab State Road Sector Project Division FEROZEPUR
Construction Division No. 1, PWD B & R, Kapurthala
PROJECTS |
| Package |
Name |
Length
(Kms) |
Scope |
Status |
Target Date |
Pre - Construction Activities |
PSRSP/WB/
RH/4/ICB |
|
34.46 |
Pavement Rehabilitation + 2 x 1.5m gravel shoulders |
completed |
- |
1. Forest Clearance (Yes)
2. Relocation of Electric Utilities (On going)
3. Relocation of Sewerage utilities
(completed) |
PSRSP/WB/
PM/5/NCB |
|
24.70 |
Pavement Rehabilitation + 2 x 1.5m gravel shoulders |
completed |
- |
1. Forest Clearance (yes)
2. Relocation of Electric Utilities (On going)
3. Relocation of Water Supply Utilities (completed)
4. Relocation of Sewerage utilities (completed) |
|
|
|